A total of £2.537 billion pounds was spent of 'non - ODA public funding'. This big amount of money was spent on the following:
- Park Security
- Elite and Community sports
- Police, army and security services
- Legacy - Park Transformation.
- Powelines
- Utilities
- Enabling works
- F10 Bridge
- Other structures, bridges and highways
- South Park site preparation
- Prescott Lock
- Landscaping
Designed by internationally acclaimed architect Zaha Hadid, the breathtaking Aquatics Centre is one of the permanent venues specially constructed for London 2012 |
A total of £0.896 billion pounds went to other Olympic Park projects such as parkwide operations, insurance, logistics for site construction, security for park construction, section 106 and masterplanning security screening, operational areas and other parkwide projects.
Tansport cost a total of £0.894 this included the DLR, Thorntons Field, Stratford Regional Station and the North London Line.